Gillespie Substation Upgrade Project

Gillespie Substation Upgrade Project

Gillespie Substation Upgrade Project

Type: Substation
Scope: Performed a 138kV/145kV substation upgrade project.
Location: Fredericksburg, Texas
Client: Lower Colorado River Authority

In March 2018, the Lower Colorado River Authority (“LCRA”) contracted Irby to perform a 138kV/145kV substation breaker replacement at the Gillespie substation near Fredericksburg, Texas. The Irby scope included replacement of six 138kV oil-filled circuit breakers with new 145kV breakers, and the installation of new control cable and junction boxes at each breaker stand. 

Throughout the project, Irby was able to display its craftsmanship specifically pertaining to aluminum bus work, bending and termination, as well as control cable installation and termination. Executed to LCRA schedule and budget, the project was successfully delivered in April 2018. 

Start Date: March 2018
Completion Date: April 2018

 

If you would like to request information on this project or submit a request for bid, click here. 

 

West Texas Substation Upgrade Project

West Texas Substation Upgrade Project

West Texas Substation Upgrade Project

Type: Substation
Scope: Performed a series of upgrade projects for four major 345kV transmission substations. 
Location: Westcentral, Texas
Client: NextEra Lonestar Transmission

Lone Star Transmission, LLC (“Lone Star”) provides transmission services to the Electric Reliability Council of Texas (>25 million customers) primarily via renewable wind energy resources from rural west Texas.

Commencing in July 2018, Lone Star contracted Irby to perform a series of upgrade projects to its four major 345kV transmission substations (Novaro, Sam, West Shackelford, and Claytonville). The project scope included the retrofit 120 Motorized Air-Breaks on existing hand-operated 345kV switches and extensive coordination was required to meet the outage/swap out schedule. Completed in October 2018, the project was delivered to specification with zero lost time incidents.

Start Date: July 2018
Completion Date: October 2018

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Canyon Substation Flood Remediation Project

Canyon Substation Flood Remediation Project

Canyon Substation Flood Remediation Project

Type: Substation
Scope: Performed a substation flood remediation project.
Location: San Marcos, Texas
Client: Lower Colorado River Authority

In recent years, persistent seasonal flood conditions in and around Hays County, Texas have impacted operations at the Lower Colorado River Authority (“LCRA”) Canyon Substation. In March 2018, LCRA contracted Irby to perform flood remediation works including the installation of a new control house and the replacement of 138kV breakers at the substation. The project involved significant coordination with client and subcontract teams to perform the rehabilitation works within constricted work areas and to a condensed LCRA outage schedule.

The Irby scope included foundation and control building construction (supported by East & Westbrook and Southwest Erectors), panel removal and relocations, pulling and termination of control cable, and installation of a microwave tower. All works were completed to the LCRA outage schedule with zero lost time incidents.

Start Date: March 2018
Completion Date: June 2018

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Comanche Solar 34.5/230kV Substation and Transmission Line Construction Project

Comanche Solar 34.5/230kV Substation and Transmission Line Construction Project

Comanche Solar 34.5/230kV Substation and Transmission Line Construction Project

Type: Substation
Scope: Constructed a 34.5/230kV substation, a 2.5 mile 34.5kV interconnection, and an underground 230kV transmission line.
Location: Pueblo, Colorado

Client: CG Power Solutions USA

Online since 2016, Xcel Energy’s (“Xcel”) 120MW Comanche Solar project is the largest solar project east of the Rockies (~3.5 megaton carbon offset), generating enough energy to power more than 31,000 homes. Under EPC contract with Xcel, CG Power USA Inc. (“CGP”) subcontracted Irby in December 2015 to construct a 34.5/230kV substation for the project including a 2.5 mile 34.5kV interconnection between the east and west solar fields and a 230kV underground transmission line from the substation to Xcel’s Comanche Generation Station. The Irby work scope was completed in under six months with zero lost time incidents.

Start Date: December 2015
Completion Date: May 2016

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Lookout Substation Construction Project

Lookout Substation Construction Project

Lookout Substation Construction Project

Type: Substation
Scope: Constructed a greenfeild 138kV substation and subsurface cabling.
Location: Garland, Texas

Client: Garland Power & Light

Garland Power & Light (“GPL”) is a not-for-profit municipal utility serving nearly 71,000 customers in and around the city of Garland, Texas. In May 2016, GPL contracted Irby to construct the greenfield 138kV Lookout substation. The project scope included all surfacing, grounding, structure erection, bus/equipment installation, cable trenching, conduit systems, testing, and substation site restoration. Irby was assisted by American Site Builders for foundations and footings construction. The project was completed on schedule and to budget in November 2016.

Start Date: May 2016
Completion Date: November 2016

 