In early May 2007 major tornado outbreaks significantly impacted portions of the Central United States. The storm cells created an estimated $268 million in damage to community infrastructure. Irby mobilized its crews to provide emergency power restoration services to the Nebraska Public Power District enabling a full return to previous power levels by months end.
Start Date: May 2007
Completion Date: May 2007
More Projects
![Storm Damage Assessment After Hurricane Ian](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2023/08/Irby-storm-assessment-team-2-510x382.jpg)
![Patterson – S. Nashville 138kV Transmission Line Rebuild Project](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2022/10/Patterson-S.Nashville-Photo-2-510x382.jpg)
![Entergy Harahan-Avondale](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2022/07/avondale2_web-510x382.jpg)
![FPL EVolution HUB](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2022/02/IMG_8169-510x382.jpg)
![New England Clean Energy Connect Transmission Line](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2022/02/IMG_6152-510x382.jpg)
![Sunshine Gateway Battery Energy Storage Center](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2021/08/IMG_0079-1-510x382.jpg)
![Manatee Battery Energy Storage Center](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2021/12/headerManatee-510x382.gif)
![Florida Power & Light Underground Lateral Hardening](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2019/10/IMG_0035_Web-510x382.jpg)
![Bozeman Road Distribution Project](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2019/04/036-510x382.jpg)
![Port St. Joe-Callaway 230kV Transmission Line Upgrade Project](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2019/03/DSC07003-510x382.jpg)
![Northeast 138kV Substation Upgrade Project](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2019/02/AEPOklahoma4-510x382.jpg)
![Colton Lane Substation Upgrade Project](https://sp-ao.shortpixel.ai/client/to_auto,q_glossy,ret_img,w_510,h_382/https://www.irbyconstruction.com/wp-content/uploads/2018/12/20180905_154003-510x382.jpg)