
Jefferson Davis Electric Cooperative 230KV T-Line System Loop Upgrade
Jefferson Davis Electric Cooperative 230KV T-Line System Loop Upgrade
Project Type: Transmission and Distribution
Scope: Upgrade approximately 105 miles of 230kV T/L with UB Distribution on several sections.
Location: Lake Charles, LA
CLIENT: Jefferson Davis Electric Cooperative (JDEC)
Irby is working in collaboration with several Quanta operating units to complete approximately 105 miles of JDEC transmission line that have been damaged from previous storms, the worst of which was Hurricane Laura in August of 2020.
The existing system is a combination of 69kV and 138kV lines that run through two Louisiana parishes. Irby’s work will upgrade these lines to a 230kV system to support future growth in these communities.
The on site team is jacking structures at the point of receipt that will then be delivered assembled to the right-of-way. There are more than 1,300 structures to complete.
Crews are also conducting wire stringing operations (both transmission and distribution under build), erecting structures in all marsh areas, and assisting with underground work at three water crossings.
The two biggest challenges on this project have been what crews have unofficially (but appropriately) labeled the two “big Ms” of Louisiana— mud and mosquitoes.
Start Date: July 2023
Completion Date: In Progress
More Projects











