Destin Resiliency and Rebuild Projects

Destin Resiliency and Rebuild Projects

Destin Resiliency and Rebuild Projects

Project Type: Transmission and New Build
Scope:
Reroute and upgrade Destin’s main transmission line to
increase ampacity.
Location: Destin, FL
Client: Florida Power & Light (FPL)

 

In June 2024, Irby Construction broke ground on the Destin Resiliency and Rebuild Projects, an initiative designed to enhance the system’s reliability and capacity for Florida Power & Light (FPL). The job involved rerouting and upgrading Destin’s primary transmission line to increase ampacity and reinforce the grid in one of the Gulf region’s most critical corridors.

The scope included installing new large concrete poles and realigning the transmission path through a densely developed, high-traffic area. Given the job’s visibility and location, Irby implemented strategic night shifts and coordinated closely with local stakeholders, including business owners, to minimize disruptions. 

To avoid costly substation shutdowns, Irby partnered with MG Dyess, a Quanta Services sister company, to perform energized work. This approach eliminated the need for outages and ensured continuous power delivery throughout the construction period.

Extensive pre-construction planning with FPL and early outreach to the local community helped streamline execution. Night construction allowed the crews to stay on schedule without impacting daytime traffic.

Completed on time and under budget, with zero safety incidents, this job delivered significant system upgrades and addressed a long-standing infrastructure need, improving overall grid resiliency for FPL customers.

Start Date: June 2024
Completion Date: August 2025

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Duke Energy – Mosaic APW AF Line

Duke Energy – Mosaic APW AF Line

Duke Energy – Mosaic APW AF Line

Project Type: Transmission
Scope:
1.9 miles of 69kV and 6.4 miles of 230kV T/L Rebuild
Location:
Wauchula, FL
Client:
Duke Energy Florida

 

This project included construction of 8.3 miles of 115kV/69kV line on the Mosaic Mine property in order to reroute an existing line around a future mine site.

The scope of work included setting 67 concrete poles and pulling 6.4 miles of 230kV, with 1.9 miles of 69kV underbuild. Irby also removed 33 structures and 4.5 miles of wire as part of the re-route.

We partnered with fellow Quanta sister company MG Dyess to build a permanent road throughout the right of way and to mat wetlands.

Because road construction was underway at the same time as the T-line work, coordination between the two companies on site was essential to its success. In addition to weekly calls with MG Dyess, the ability to complete the project efficiently required communication and coordination at the field level. Irby and MG Dyess superintendents were key players in the project’s ultimate success.

Thanks to this highly effective collaborative relationship, the work was completed on time and on budget.

Start Date: October 2023
Completion Date: April 2024

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Jefferson Davis Electric Cooperative 230KV T-Line System Loop Upgrade

Jefferson Davis Electric Cooperative 230KV T-Line System Loop Upgrade

Jefferson Davis Electric Cooperative 230KV T-Line System Loop Upgrade

Project Type: Transmission and Distribution
Scope:
Upgrade approximately 105 miles of 230kV T/L with UB Distribution on several sections.
Location:
Lake Charles, LA
CLIENT: Jefferson Davis Electric Cooperative (JDEC)

Irby is working in collaboration with several Quanta operating units to complete approximately 105 miles of JDEC transmission line that have been damaged from previous storms, the worst of which was Hurricane Laura in August of 2020.

The existing system is a combination of 69kV and 138kV lines that run through two Louisiana parishes. Irby’s work will upgrade these lines to a 230kV system to support future growth in these communities.

The on site team is jacking structures at the point of receipt that will then be delivered assembled to the right-of-way. There are more than 1,300 structures to complete.

Crews are also conducting wire stringing operations (both transmission and distribution under build), erecting structures in all marsh areas, and assisting with underground work at three water crossings.

The two biggest challenges on this project have been what crews have unofficially (but appropriately) labeled the two “big Ms” of Louisiana— mud and mosquitoes.

Start Date: July 2023
Completion Date: In Progress

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Patterson – S. Nashville 138kV Transmission Line Rebuild Project

Patterson – S. Nashville 138kV Transmission Line Rebuild Project

Patterson – S. Nashville 138kV Transmission
Line Rebuild Project

Type: Transmission
Scope: 138kV Rebuild
Location: Southwest Arkansas
Client: AEP Southwestern Electric Power Company

Southwestern Electric Power Co. (SWEPCO), an American Electric Power company, serves more than 543,000 customers in Northwest and Central Louisiana, Northeast Texas and the Texas Panhandle, and Western Arkansas. In October 2021, Irby Construction began a 25-mile rebuild of the Patterson to S. Nashville 138kV transmission line for SWEPCO. 

Located in the southwest corner of Arkansas, the project includes more than 240 structures that meander through marshy territory on Arkansas Heritage Commission property, U.S. Army Corp of Engineers land, and numerous wetland areas. 

This 138kV single circuit transmission project consists of three eight-mile sections and has planned outages so the Irby crew can perform pole work on de-energized lines. The first section is 8.8 miles long and consists of 79 structures. The second section is 8.3 miles with the replacement of 83 structures, and the final section is roughly 8.1 miles with 80 structures. The final line is scheduled to be in-service on November 30, 2023. 

To assist with overall access of the area, Irby has contracted with affiliate company MG Dyess to clear obstacles and tackle the challenging wetland conditions. For the more than 30 Irby crew members who are wrecking out and rebuilding the existing transmission line, MG Dyess is laying thousands of wood mats to access work areas. 

NorthStar Energy Services, another affiliate company, is providing support services by drilling and pouring foundations as well as drilling and setting bases for the direct embed structures. 

From creating entry and overcoming barriers to setting foundations and poles, these coordinated efforts allow Irby to work efficiently and effectively. Irby is exceeding expectations on this job and is committed to the absolute performance required to safely deliver this project on time and within budget. 

Start Date: October 2021
Scheduled Completion: In Progress

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Entergy Harahan-Avondale

Entergy Harahan-Avondale

ENTERGY HARAHAN-AVONDALE 230kV RIVER CROSSING TRANSMISSION LINE

Type: Transmission
Scope: Water Crossing, Emergency Restoration
Location: New Orleans, Louisiana
Client: Entergy New Orleans

Entergy New Orleans provides electricity to more than 209,000 customers in Orleans Parish, Louisiana. On Sunday, August 29, 2021, Hurricane Ida made landfall as a Category 4 hurricane with sustained winds of 150 mph. The New Orleans area suffered damage causing outages for approximately 895,000 customers.

As a result of Hurricane Ida, a 475-foot lattice transmission tower in Avondale, a suburb on the west bank of the Mississippi River, was damaged and fell with conductor lines landing in the river. The tower on the Harahan side of the river remained intact with the conductor lines attached. This was a primary circuit for New Orleans and power was rerouted to restore electricity for customers until the damage could be repaired.

Entergy New Orleans contracted with Irby to manage the project from beginning to end. The removal of the destroyed transmission tower’s lines in the Mississippi River was a national priority. Efforts included coordinating with the Army Corps of Engineers, U.S. Coast Guard, Levee District, Louisiana State Police, Jefferson Parish EOC, the Governor’s Office of Homeland Security and other agencies to ensure safety and minimize risks.   

To safely remove the wire from the tower, clearing the downed conductor lines was completed by Dem-Tech through a series of controlled detonations. Explosives were attached to the conductor lines on both sides of the tower and demoed in sections. 

Once the lines and old towers were cleared away, Boh Bros. Construction Co., LLC, completed pile driving work and Irby sister company Legend Foundation Services installed anchor bolted piers to resist uplift forces that might otherwise cause the new tower and lines to be extracted from the ground.

With foundations in place, Irby, TNT Crane, and A&J Steel erected two 475-foot PyraMAX towers to supersede the old ones. With only 6 hours a day permitted by authorities to shut down major river traffic, Irby has begun stringing the lines using barges across the 3,700-foot span of the Mississippi. Once that is complete, energizing the lines is the last step in bringing this major transmission system back to life.

Irby is proud to have been recognized by our client, Entergy, for our work on this project as a Premier Vendor for Customer Centricity. Watch the Premier Vendor Award video here. 

For more details and background on this project, visit Entergy’s website.
Click here to read the T&D World feature on this project.

 

 

If you would like to request information on this project or submit a request for bid, click here.